OPINION
CARPENETI, Justice.
We are asked to determine whether a Department of Administration hearing officer erred when he selected the remedy for a defective procurement process. Several months after a procurement contract for a long term lease was awarded, the hearing officer concluded that three separate irregularities had occurred during the proposal evaluation process. After conducting an analysis under AS...