Justice HEARN.
This case arises from a grant of partial summary judgment in favor of an architectural firm finding a contract existed between it and the City of Columbia. On certiorari, the City concedes a contract exists, but argues the contract terms have been satisfied. We find the City's arguments are unpreserved and affirm as modified.
FACTUAL/PROCEDURAL BACKGROUND
In April 2003, the City entered into a Memorandum of Understanding (MOU) with...