In this appeal, the South Carolina Public Service Commission ("Commission") determined South Carolina Electric & Gas Company ("SCE&G") was entitled to recover contingency costs under the Base Load Review Act.
FACTUAL/PROCEDURAL BACKGROUND
In 2005, SCE&G identified the need for additional base load power plants