IN RE NARRAGANSETT ELEC. CO.

No. 2018-40-M.P.

276 A.3d 363 (2022)

IN RE NARRAGANSETT ELECTRIC COMPANY d/b/a National Grid E-183 115 kV Transmission Line Relocation Project.

Supreme Court of Rhode Island.

June 17, 2022.


Attorney(s) appearing for the Case

Patrick C. Lynch, Esq. , Jeffrey B. Pine, Esq. , for Petitioners.

W. Mark Russo, Esq. , Steven J. Boyajian, Esq. , Marc DeSisto, Esq. , for Respondents.

Present: Suttell, C.J., Goldberg, Robinson, Lynch Prata, and Long, JJ.


OPINION

This Court issued a writ of certiorari to review an order of the Energy Facility Siting Board (the board or EFSB) concerning the relocation of power lines across the Providence and Seekonk Rivers. The petitioners, the City of Providence; Friends of India Point Park (FIPP); Procaccianti Companies...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases