MATTER OF OKLA. CAPITOL IMPR. AUTHORITY

Case No. 119,868.

507 P.3d 1256 (2022)

2022 OK 31

In the MATTER OF the Application of the OKLAHOMA CAPITOL IMPROVEMENT AUTHORITY FOR the APPROVAL OF NOT TO EXCEED $200,000,000 STATE HIGHWAYS CAPITAL IMPROVEMENT NOTES, SERIES 2021 (Oklahoma Department of Transportation TIFIA RPI Project).

Supreme Court of Oklahoma.

Filed April 5, 2022.


Attorney(s) appearing for the Case

Jered T. Davidson , The Public Finance Law Group, PLLC, Oklahoma City, for Petitioner.

Thomas R. Schneider , Oklahoma Office of Attorney General, Oklahoma City, OK, for Petitioner.


¶1 In 2021, the Oklahoma Department of Transportation (ODOT), released an eight-year construction plan report, identified as the Oklahoma Transportation Commission Construction Work Plan (FFY 2021-FFY 2028). Within the Plan, ODOT recommended implementation of the Rural 2-Lane Advancement and Management Plan (RAAMP), which called...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases