All second third-party plaintiff's (APS Contracting) notices of claim were either untimely or facially insufficient, or both, for failing to state APS Contracting's claimed damages under the requirements of the parties' contract (see Universal Constr. Resources, Inc. v New York City Hous. Auth., 192 A.D.3d 470, 471 [1st Dept 2021]; Matter of Intercontinental Constr. Contr., Inc. v New York City Hous. Auth., 173 A.D.3d 453, 454 [1st Dept 2019]; Start El.,...