The purchase order at issue contains a clause under which indemnity lies in favor of Structure Tone where the claim arises in any manner from the acts or omissions of FRP, its officers, directors, agents, employees, and subcontractors "in connection with the performance of any work by Subcontractor pursuant to this purchase order." FRP's interpretation of the clause as only being triggered where it performs the work itself would impermissibly render that portion of the provision...