Supreme Court properly denied defendant's motion to dismiss the breach of contract claim. The complaint alleges that defendant breached its obligation under Section 2(b) of the Commitment Letters, the governing contracts, on January 18, 2018, March 2, 2018, and April 16, 2018, "by providing false, incomplete and misleading Project Status Notices certifying that there was no Project Delay" in completing construction