Appellate Division of the Supreme Court of New York, First Department.
The motion court properly dismissed the complaint as untimely. "[A] cause of action arising out of defective construction accrues upon completion of the contractual work" (Town of Oyster Bay v Lizza Indus., Inc.,22 N.Y.3d 1024, 1029 [2013]). This is so "no matter how a claim is characterized in the complaint because all liability for defective construction has its genesis in the contractual...