Defendant SLSCO is a general contractor that entered into a public works contract with the New York City Department of Environmental Protection (DEP) for the repair and restoration of private homes and multiple dwellings damaged by Hurricane Sandy. SLSCO hired subcontractors, including defendant PMJ Electrical Corp. (PMJ) to perform the work required under the prime contract. SLSCO agreed in the prime contract with the DEP that workers, laborers and mechanics employed on...