It is undisputed that plaintiff failed to satisfy a condition precedent to recovering disputed costs for extra work on which defendant forced price reductions. Although plaintiff gave detailed written statements contesting defendant's determinations of the fair and reasonable value of the extra work pursuant to section 8.01 (B), it failed to give verified statements pursuant to section 11.03(A) of the contractual General Conditions.
Nevertheless, we conclude that...