MTR. OF AIR ENERGY v. COUNTY OF CORTLAND

12-554.

39 Misc.3d 234 (2012)

955 N.Y.S.2d 769

2012 NY Slip Op 22371

In the Matter of AIR ENERGY TCI, INC., Petitioner, v. COUNTY OF CORTLAND, Respondent.

Supreme Court, Cortland County.

December 14, 2012.


Attorney(s) appearing for the Case

Bond, Schoeneck & King, Syracuse ( Kevin M. Bernstein and Suzanne M. Messer of counsel), for petitioner. Edward R. Purser , County Attorney, Cortland, and Patrick M. Snyder , Cortland, for respondent.


OPINION OF THE COURT

PHILLIP R. RUMSEY, J.

Petitioner proposes to develop a project in the Towns of Cortlandville, Homer, Solon and Truxton in Cortland County, to generate electricity from wind, which it identifies as the Crown City Wind Energy Project (the project). The project is believed to be the largest ever proposed for Cortland County and includes construction of 44 wind turbines that are 492 feet tall, over 20 miles of access roads, 30 miles of buried...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases