We have previously stated — in a case involving the same contract provision as in the instant case — "The construction contract entered into between plaintiff and the City unambiguously precluded plaintiff from commencing a plenary action for damages upon a determination by the City that plaintiff had defaulted under the contract. Plaintiff's remedy was to commence a CPLR article 78 proceeding challenging the determination of default, which it failed to do"...
Let's get started
Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.
- Updated daily.
- Uncompromising quality.
- Complete, Accurate, Current.