The Supreme Court properly determined that the second cause of action, to recover damages for breach of contract, was time-barred because it was not commenced during the one-year period of limitation set forth in section 127 of the City Charter of the City of New Rochelle. Contrary to the plaintiff's contention, the period of limitation began to run when its damages became...