The motion court properly denied Pace's motion for summary judgment in this action where plaintiff was injured when the scaffold on which he was standing slipped into an open, uncovered hole in the concrete floor, and tipped over. The record shows that the contract between Pace and the construction manager of the renovation project required Pace to cut, fit, patch and protect its work. Although the specifications portion of the contract provides that the openings left in...