Respondents' contentions notwithstanding, the long-term monitoring measures, developed and implemented in their entirety after the final EIS was issued in October 2006, constituted "changes proposed for the project" (6 NYCRR 617.9 [a] [7] [i] [a]). Given, among other things, the Department of Environmental Conservation's July 2006 directive to SCA to develop a site management plan, which by definition under the applicable Brownfield Cleanup Program (BCP) (see ECL art...