Ordered that the order is reversed insofar as appealed from, on the law, with costs, and the plaintiff's motion for summary judgment on so much of the complaint as alleged violations of Labor Law § 240 (1) is granted.
The plaintiff, a laborer working on a demolition project, was instructed by his supervisor to cut and remove a horizontal pipe located 9 to 10 feet above the ground. The pipe was suspended by hangers connected to the ceiling. The plaintiff ascended...