Ordered that the order is affirmed insofar as appealed from, with costs.
Nonparty KeySpan Electric Services, LLC, now known as National Grid (hereinafter National Grid) entered into a contract with the defendant on March 13, 2009, in which the defendant agreed to install approximately 46,000 feet of underground power transmission cable from Bridgehampton to Southampton, on Long Island. The defendant entered into a subcontract (hereinafter the Subcontract) with the...