Ordered that the order entered March 10, 2010, is affirmed insofar as appealed from, with costs.
During the summer of 2007, the defendants contracted with the plaintiff, Quick Start Construction Corp., to perform renovations to their home in Patchogue. The work commenced in September 2007. In December 2007 the plaintiff presented the defendants with a contract for additions and extras. The defendants refused to sign the proposed contract or to pay any further amounts...