PEATROSS, J.
This is an appeal from a judgment sustaining an exception of peremption/prescription and dismissing the claims of Bossier Parish School Board ("BPSB") against Cochran Construction Company, Inc. ("Cochran") for damages arising out of the construction of the roof on Haughton Middle School. The trial court found that the five-year peremptive period embodied in the Louisiana Public Works Act, La. R.S. 38:2189, was applicable to the claims of BPSB and that...