REY COLIMAN CONTRACTORS, INC. v. PCL CONST., SERV. INC.

No. A09A0106.

676 S.E.2d 298 (2009)

REY COLIMAN CONTRACTORS, INC. v. PCL CONSTRUCTION SERVICES, INC.

Court of Appeals of Georgia.

March 24, 2009.


Attorney(s) appearing for the Case

Swift, Currie & Hancock, Andrew R. McBride, Atlanta, for appellant.

Moye, O'Brien, O'Rourke, Pickert & Martin, J. Andrew Williams, Maitland, FL, Thomas A. Nash Jr., Savannah, for appellee.


ANDREWS, Presiding Judge.

Was a subcontractor (Rey Coliman Contractors, Inc.) required to comply with the provisions of OCGA § 44-14-361.5 to perfect its special lien for labor and materials even if the contractor (PCL Construction Services, Inc.) failed to comply with the provision in subsection (b) of the statute requiring it to post a copy on the project site of the "Notice of Commencement" of work? The short answer is yes: Although OCGA § 44-14-361.5...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases