PER CURIAM.
We reverse the final judgment in favor of appellee on its breach of contract claim. First, we find that the record does not support appellee's claims of substantial compliance. Because time was "of the essence" in the post-closing agreement, appellee's failure to complete construction of RCA Boulevard by the deadline in the contract constituted a material breach. Sublime, Inc. v. Boardman's Inc.,