SACRAMENTO MUNICIPAL UTILITY DISTRICT, Petitioner
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent.
California Independent System Operator Corporation, et al., Intervenors.
United States Court of Appeals, District of Columbia Circuit.https://leagle.com/images/logo.png
Before: BROWN, GRIFFITH and KAVANAUGH, Circuit Judges.
United States Court of Appeals, District of Columbia Circuit.
PER CURIAM:
Following the California energy crisis of 2000-01, the California Independent System Operator (California ISO or the ISO) began the process of redesigning California's electricity market. The Federal Energy Regulatory Commission (FERC or the Commission) issued a series of orders providing guidance on California ISO's proposals. Ultimately, in four orders issued between 2006 and 2008, the Commission approved the ISO's new market design, rejecting the numerous...
Let's get started
Welcome to the leading source of independent legal reporting Sign on now to see your case. Or view more than 10 million decisions and orders.
Updated daily.
Uncompromising quality.
Complete, Accurate, Current.
Listed below are the cases that are cited in this Featured Case. Click the citation to see the full
text of the cited case. Citations are also linked in the body of the Featured Case.
Cited Cases
No Cases Found
Listed below are those cases in which this Featured Case is cited. Click on the case name to see the
full text of the citing case.