The court properly dismissed the complaint as against the City. The construction contract entered into between plaintiff and the City unambiguously precluded plaintiff from commencing a plenary action for damages upon a determination by the City that plaintiff had defaulted under the contract. Plaintiff's remedy was to commence a CPLR article 78 proceeding challenging the determination of default, which it failed to do. Plaintiff's termination of the contract prior to the...