We affirm the dismissal of the claim for delay damages upon the ground that it is premature. The contract bars claims against the construction manager "on account of the Contract Price for the Project" until the completion of available mechanic's lien enforcement actions, and two such causes of action are alleged in the fourth amended complaint. Although plaintiff contends that the clause requiring exhaustion of Lien Law remedies is unenforceable, the provision at issue does...