Rose, J.
Pursuant to a written contract with defendant, plaintiff agreed to reconstruct taxiways and runways at the Elmira/ Corning Regional Airport. Third-party defendant, McFarland-Johnson, Inc. (hereinafter MFJ), an engineering firm, designed and supervised the project. Before reconstruction of one of the work areas began, the parties executed a change order providing that, rather than excavate the existing pavement, plaintiff would mill it and then apply new pavement...