Rose, J.
Andrew R. Mancini Associates, Inc. (hereinafter ARM), acting as general contractor, subcontracted with third-party defendant R&S Steel, LLC to perform all steel work on a construction project. R&S, in turn, subcontracted with plaintiff to perform the steel erection work. After completion of its work, plaintiff sought to secure payment by filing a mechanic's lien and commencing this action against defendant, the surety on ARM's payment bond. The bond...