The Energy Facilities Siting Board (board) conditionally approved a petition filed jointly by Cape Wind Associates, LLC (Cape Wind), and Commonwealth Electric Company, doing business as NSTAR Electric (NSTAR) (together, applicants), to build and operate two 115 kilovolt underground and undersea electric transmission lines approximately eighteen miles in length. The transmission lines would connect an offshore...