The condition precedent to arbitration requiring a decision by the project architect on all claims "arising prior to the date final payment is due" is inapplicable, since the claim here was made after final payment became due, i.e., after the architect had approved petitioner's final request for payment. Petitioner's other claims were improperly advanced for the first time either on reargument (see William P. Pahl Equip. Corp. v Kassis, 182 A.D.2d...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases