Pursuant to an April 2003 agreement, plaintiff was engaged by defendant NED to act as general contractor on a project to build five three-family homes. The work was to be completed within one year at a price of $2,814,766. However, after nine months, only the exterior foundation walls had been poured. NED terminated the agreement in February 2004, and plaintiff filed a mechanic's lien in early March. The notice of lien represents that plaintiff was owed $435,431.96 for its...