Justice BOWMAN delivered the opinion of the court:
This case raises the issue of which of three limitations periods applies in an action for the breach of a written indemnity agreement following a surety's payout on a construction bond: the two-year limitations period of section 13-204 of the Code of Civil Procedure (Code) (735 ILCS 5/13-204 (West 2004)) for contribution and indemnity actions; the four-year limitations period of section 13-214(a) of the Code (735...