Kane, J.
Plaintiff, which operates an indoor fish hatchery, entered into a contract whereby defendant would supply a 13,000-gallon oxygen storage tank to plaintiff's facility. The contract required that the tank be delivered during the week of June 21, 1999, with a $400 per day liquidated damages provision, denoted a "fine," in the event of a delay. Defendant provided several 50-gallon cylinders in September 1999, then a 3,000-gallon tank in December 1999 or January...