MEMORANDUM OPINION AND ORDER
LEON, District Judge.
Before the Court are the parties' cross motions for summary judgment seeking a ruling as to whether the Environmental Protection Agency ("EPA") has unreasonably delayed the suspension or cancellation
ANALYSIS
Summary judgment is appropriate when the pleadings and the record demonstrate that "there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law." FED. R. CIV. P. 56(c). In determining whether a genuine issue of material fact is in dispute, "[t]he evidence of the non-movant is to be believed, and all justifiable inferences are to be drawn in his favor." Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).
Although judicial review of agency action is typically reserved for final agency actions, 5 U.S.C. § 704, the Administrative Procedures Act ("APA") authorizes the Court to review agency action where a plaintiff alleges that the government has either unlawfully withheld or unreasonably delayed action. 5 U.S.C. § 706(1); see also Cobell v. Norton, 240 F.3d 1081, 1095 (D.C.Cir.2001). In its complaint, Beyond Pesticides alleges that because of EPA's failure "over two decades to address issues raised in its [Rebuttable Presumption Against Registration review] of 1978 . . ., EPA has either unreasonably delayed or constructively denied Beyond Pesticides' June 2, 1997, December 21, 1999, July 21, 2000, April 19, 2001, December 21, 2001, February 26, 2002, and July 25, 2002 petitions" seeking, among other things, the cancellation and suspension of all uses of the wood preservative pesticides. Compl. ¶ 63. Accordingly, this Court must determine whether EPA has violated the APA by unlawfully withholding or unreasonably delaying agency action. For the following reasons, the Court concludes EPA did neither.
The Court must first "ascertain the length of time that has elapsed since the agency came under a duty to act." Cutler v. Hayes, 818 F.2d 879, 897 (D.C.Cir.1987). Since a court is only able to compel an agency to take action that is legally required, Norton v. S. Utah Wilderness Alliance, 542 U.S. 55, 124 S.Ct. 2373, 2379, 159 L.Ed.2d 137 (2004), this Court must analyze the delay by EPA from the point where the agency first became obligated to act. Although the plaintiff argues that the delay should be measured from either 1993, when steel producers submitted information to EPA regarding the viability of alternatives to the wood preservative pesticides, or from 1997, when it made its first request for regulatory action, Pl.
The D.C. Circuit first outlined the so-called TRAC factors in 1984 to provide guidance to courts assessing whether agency action was unreasonably delayed. Those factors are:
Telecommunications Research & Action Ctr., 750 F.2d at 79-80 (internal citations omitted).
The first two TRAC factors can be considered simultaneously because the reasonableness of any delay must take into consideration any congressional expectations or mandates regarding the speed at which a proceeding should advance. In re Monroe Communications Corp., 840 F.2d 942, 945 (D.C.Cir.1988); Cutler, 818 F.2d at 897 (finding that "[t]he reasonableness of the delay must be judged `in the context of the statute' which authorizes the agency's action") (citation omitted). Indeed, absent a statutory timetable in the enabling statute, an agency is entitled to considerable deference in how expeditiously it proceeds with agency action. Sierra Club v. Thomas, 828 F.2d 783, 797 (D.C.Cir.1987). In this case, although EPA is not bound by a statutory mandate to answer Beyond Pesticides' petitions in a particular time frame, EPA has recognized that it must answer the petitions and has notified Beyond Pesticides that it will either grant or deny the petitions when it completes the reregistration process, Def. Memo. at 26, thereby satisfying these factors.
The third, fourth and fifth TRAC factors relate to the agency's prioritization of the agency action requested. Specifically, the third factor demonstrates that delays affecting human health and welfare are less tolerable than delays affecting economic interests. Sierra Club, 828 F.2d at 798. Our Circuit Court, however, has found that the third "factor alone can hardly be considered dispositive when . . . virtually the entire [EPA] docket . . . involves issues of this type." Id. (discussing the competing interests at the EPA and finding that "[g]iven that Congress provides EPA with finite resources to satisfy these various responsibilities, the agency cannot avoid setting priorities among them"). As to the fourth and fifth factors, an agency is in the best "position to view its projects as a whole, estimate the prospects for each, and allocate its resources in the optimal way." In re Barr Labs., Inc., 930 F.2d 72, 76 (D.C.Cir.1991). In fact, our Circuit Court has held that the impact of the delay is irrelevant where "putting
Finally, the sixth TRAC factor allows the Court to weigh any alleged impropriety against the other factors in the test. Although the Court need not find that an impropriety existed in order to determine that the delay was unreasonable, "[w]here the agency has manifested bad faith . . ., the agency will have a hard time claiming legitimacy for its priorities." In re Barr Labs., 930 F.2d at 76. Here, however, the Court is not convinced that Beyond Pesticides has overcome "the well established presumption that public officials . . . act in good faith and are conscientiously proper in the discharge of their duties." Bayshore Res. Co. v. U.S., 2 Cl.Ct. 625, 632 n. 4 (1983).
Thus, in weighing the six factors outlined by our Circuit Court, this Court is satisfied that the delay in responding to Beyond Pesticides' petitions is reasonable and justified because Congress established the priority in which EPA should evaluate the eligibility for reregistration of registered pesticides and EPA does not appear to be either "singling [Beyond Pesticides] out for bad treatment or asserting utter indifference to a congressional deadline." In re Barr Labs., 930 F.2d at 76. Accordingly, notwithstanding EPA's slow, but deliberate, pace during the reregistration process, its delay is not unreasonable and judicial intervention is not justified.
ORDER
For the reasons set forth above, it is this 21
Comment
User Comments