SOUTHERN CAL. EDISON CO. v. PUC

No. B171050.

18 Cal.Rptr.3d 435 (2004)

121 Cal.App.4th 1303

SOUTHERN CALIFORNIA EDISON COMPANY, Petitioner, v. PUBLIC UTILITIES COMMISSION, Respondent; Center for Energy Efficiency and Renewable Technologies, Real Party in Interest.

Court of Appeals of California, Second District, Division One.

As Modified on Denial of Rehearing September 27, 2004.

Review Denied January 19, 2005.


Attorney(s) appearing for the Case

Stephen E. Pickett, Michael D. Mackness and Erin K. Moore, Rosemead, for Petitioner.

Randolph L. Wu, Mary F. McKenzie and Karen Paull, San Francisco, for Respondent.

Sara Steck Myers, San Francisco; Ellison, Schneider & Harris, Christopher T. Ellison, Jeffery D. Harris and Lynn M. Haug, Sacramento, for Real Party in Interest.


MALLANO, J.

To accommodate the connection of newly created sources of electrical energy to a transmission facility that is part of the national grid, it is often necessary to up-grade the grid at the point of interconnection. Federal law, as set forth in a recent order of the Federal Energy Regulatory Commission (FERC), states that the generator of the energy is initially responsible for the costs of the upgrade but further provides that the owner of the transmission...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases