Plaintiff, the general contractor for construction at a restaurant to be operated at Grand Central Station by Zocalo and its principal, Shapiro, alleges breach of contract and nonpayment for work performed, seeking a balance due of $257,233.80. Defendants counterclaim, inter alia, that delays in completing the work, attributable to the additional counterclaim defendants, caused them four months worth of lost profits, estimated at more than $400,000.