Plaintiff alleges that it performed work and provided materials at the job site between January 12, 2000 and May 7, 2001, submitted invoices totaling $1,145,325.14 between February 7, 2000 and May 15, 2001, and that a balance of $297,693.54 remains due on its invoices. The motion court dismissed the complaint on the basis of a document denominated "Full and Final Waiver of Lien," signed by plaintiff and dated October 5, 2001, which states that plaintiff had accepted the amount...