PER CURIAM.
This appeal arises from a dispute by both parties to a design-build contract, each party claiming that the other breached the terms of their agreement. The arbitrator found that Archer-Edwards Corporation breached the contract, based on which the arbitrator awarded certain damages to S & J Enterprises of Fort Lauderdale, Inc. The complete arbitration award was subsequently vacated by the lower court at Archer-Edward's request.