Lahtinen, J.
Claimant, an employee of Pike Construction Company, was working on a project that Pike had contracted to perform on premises owned by defendant. As part of the project, claimant and a coworker, William Smith, were directed to remove fourinch PVC piping that was partially filled with concrete debris from a pipe chase. The pipe chase was estimated to be 6 feet wide and 12 feet high. The PVC pipes were suspended by wire approximately two feet below the ceiling...