This is an action to dismiss a construction lien as invalid and frivolous. The superior court ruled that the lien was invalid because it was filed beyond the 90-day time limit required by the statute. The court also ruled that, because the lien was filed beyond the 90-day time limit, it was also frivolous. The subcontractor, Intermountain Electric, Inc., then filed a second lien. We conclude that the first lien...