OPINION
MAES, Chief Justice.
{1} Appellant Tri-State Generation and Transmission Association, Inc. (Tri-State) sought court orders allowing it to enter and survey land owned by Appellees. Tri-State plans to condemn the land, if suitable, in order to build a new electrical transmission line. The district court concluded that the New Mexico Public Regulatory Commission (PRC) has exclusive jurisdiction over Tri-State and therefore dismissed both applications...