Ordered that the order is affirmed insofar as appealed from, with costs.
Stefanos Tsatsakos (hereinafter Tsatsakos) and a coworker, window washers, were engaged in raising a scaffold at the Citicorp Building in Long Island City. Tsatsakos was inside the scaffold, which was approximately one foot above the 48th floor setback and was suspended by cables from the roof of the building. The scaffold was equipped with a control that enabled it to be raised and lowered along...