PER CURIAM.
The contractor defendant, Team Land Development, Inc., and the contractor's surety, USF & G, appeal the granting of summary final judgment in favor of the subcontractor plaintiff, Anzac, Inc. We reverse because Anzac failed to provide the releases required by the subcontract as a condition precedent to payment.
Team Land entered into a contract with the South Florida Water Management District for work on a discharge canal. USF & G was the...