PALMER, J.
G.E.L. Recycling, Inc. appeals the trial court's final order entering summary judgment in favor of Atlantic Environmental, Inc. and rejecting G.E.L.'s claim for payment due for work completed on a construction project. Concluding that the parties' contract does not contain a clear and unambiguous "pay when paid" clause, we reverse.
G.E.L. filed suit against Atlantic Environmental alleging claims of breach of contract. The complaint explained that...