EASTERBROOK, Circuit Judge.
Qualitech Steel Corporation had a short, unhappy, and expensive life. Formed in 1996 to exploit new technologies for producing specialty steels, Qualitech spent more than $400 million building two plants. Both took longer to build than expected, were more costly to construct and operate than expected, and generally performed below expectations. By March 1999, when it entered bankruptcy, Qualitech had not reached full scale and was losing...