ORDER
The Opinion filed August 11, 1999, slip op. 8973, and appearing at 187 F.3d 1007 (9th Cir.1999), is amended as follows:
With this amendment, the panel has voted unanimously to deny the petitions for rehearing of respondent Federal Energy Regulatory Commission, petitioners American Rivers et al., respondent-intervenor Eugene Water and Electric Board, and the federal intervenors. Judges McKeown and Wardlaw have voted to reject the suggestions for rehearing en banc of respondent Federal Energy Regulatory Commission, petitioners American Rivers et al., and respondent-intervenor Eugene Water and Electric Board, and Judge Leavy has so recommended.
The full court has been advised of the suggestions for rehearing en banc and no active judge has requested a vote on whether to rehear the matter en banc. Fed. R.App. P. 35.
The petitions for rehearing are DENIED and the suggestions for rehearing en banc are REJECTED.
OPINION
WARDLAW, Circuit Judge:
At stake in these consolidated petitions is the continued operation of two hydro-electric
I
The license under review authorizes the continued operation of the 14.5-megawatt Leaburg Hydroelectric Project and the 8-megawatt Walterville Hydroelectric Project for a duration of 40 years. See Eugene Water & Elec. Bd., 78 Fed. Energy Reg. Comm'n Rep. (CCH) ¶ 62,207, at 64,693 (Mar. 24, 1997) ("Order Issuing New License").
The Leaburg development, the project's upstream facility, consists of a dam, canal, powerhouse facilities, a tailrace, and a power substation. The dam creates a fifty-seven acre backwater called Leaburg Lake which extends approximately 1.5 miles upstream. On each side of the dam are fish ladders, only one of which is operational. On the upstream side of the dam, intake gates divert water through a downstream migrant fish screen into the five-mile Leaburg power canal. The diverted water passes through the power plant forebay into the two-turbine Leaburg powerhouse. The water returns to the McKenzie River through a 1,100-foot tailrace.
Six miles downstream, headworks divert water from the McKenzie into the unscreened, four-mile Walterville power canal. The Walterville canal feeds into a single-turbine powerhouse from which water returns to the McKenzie through a two-mile tailrace. The Walterville canal bypasses a 7.3 mile stretch of the McKenzie.
The Director issued the disputed license on March 24, 1997, pursuant to the FPA.
During the relicensing deliberations, the Director considered the final environmental impact statement prepared by the Commission's environmental staff.
The Commission's staff also examined the conditions submitted by the state and federal fish and wildlife agencies under color of FPA sections 10(j) and 18.
Two months after the section 10(j) dispute resolution meeting between the resource agencies and Commission staff, the Secretary of Interior filed modifications to its section 18 prescriptions for the Director's consideration. These modified prescriptions met with substantially the same results as the resource agencies' earlier submissions. Like the Commission staff before him, the Director found that the Secretary's prescriptions relating to fish ladders and fish screens constituted section 18 fishways but nevertheless did not incorporate the submissions as prescribed, electing instead to establish a plan under which EWEB would "consult with the agencies in developing final designs and monitoring plans for Commission approval." Id. at 64,699 (implementing license articles 416, 418, and 420). As to the remaining prescriptions, the Director held that the submissions, even as modified, were beyond the scope of section 18. See id. at 64,700. The Director explicitly stated for the record the basis for the rejection or reclassification of most of the submissions. See id. at 64,699-700.
American Rivers, the United States Department of the Interior, the National Marine Fisheries Service ("NMFS"), and ODFW timely sought rehearing, forwarding the same arguments which had divided the parties since the issuance of the final environmental impact statement.
II
As a preliminary matter, we discuss the methodology we employ in reviewing the Commission's licensing decision. The petitioners contest the Commission's decision under two statutes, the FPA and NEPA. The petitioners first challenge the sufficiency of the Commission's environmental analysis under the FPA and NEPA, arguing that the terms of the new license exacerbate the already degraded conditions in the McKenzie River basin. The petitioners next contend that the FPA does not authorize the Commission to make threshold determinations of whether a given agency recommendation or proposed license condition satisfies the requirements of FPA section 10(j) or section 18. The petitioners' FPA contentions require consideration of substantive issues of statutory construction, whereas the petitioners' NEPA challenges require analysis of the Commission's compliance with NEPA's various procedural requirements. These two lines of inquiry proceed along different analytic paths which are subject to separate standards of review.
Under the FPA, we grant conclusive effect to the Commission's findings of fact if such findings are supported by substantial evidence. See 16 U.S.C. § 825l(b); Muckleshoot Indian Tribe v. Federal Energy Regulatory Comm'n, 993 F.2d 1428, 1430 (9th Cir.1993). Where, however, the petitioners call into question the Commission's understanding of its statutory mandate, our review is de novo. See Skokomish Indian Tribe v. Federal Energy Regulatory Comm'n, 121 F.3d 1303, 1306 (9th Cir.1997). The Commission's interpretation of the FPA implicates the now familiar process of reviewing agency actions exemplified by the Supreme Court's watershed opinion in Chevron U.S.A., Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984). Chevron set forth the two-part test against which courts review an agency's construction of the statute it administers. See id. at 842-43, 104 S.Ct. at 2781-82. Under the Chevron formulation:
Id.; accord Rainsong Co. v. Federal Energy Regulatory Comm'n, 106 F.3d 269, 272 (9th Cir.1997). The two-step Chevron framework thus allows this Court to defer to the Commission's interpretations of the statutory provisions it administers, but we remain "the final authority on issues of statutory construction and must reject administrative constructions which are contrary to clear congressional intent." Natural Resources Defense Council v. United States Dep't of Interior, 113 F.3d 1121, 1124 (9th Cir.1997) (citing Chevron, 467 U.S. at 843 n. 9, 104 S.Ct. at 2781 n. 9) (internal quotations omitted).
A different set of principles guides our review under NEPA because "NEPA does not mandate particular substantive results, but instead imposes only procedural requirements." Laguna Greenbelt, Inc. v. United States Dep't of Transp., 42 F.3d 517, 523 (9th Cir.1994) (citing Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U.S. 519, 558, 98 S.Ct. 1197, 1219, 55 L.Ed.2d 460 (1978)). Our task under NEPA therefore "is simply to ensure that [FERC] has adequately considered and disclosed the environmental impact
These standards reflect the axiomatic distinction between "the strong level of deference we accord an agency in deciding factual or technical matters [and] that to be accorded in disputes involving predominantly legal questions." Alaska Wilderness Recreation and Tourism Ass'n v. Morrison, 67 F.3d 723, 727 (9th Cir.1995). It is with these principles that we turn to merits of the petitions.
III
The petitioners first object to the Commission's use of existing environmental conditions at the Leaburg-Walterville Project as a "baseline"
A. The Choice of Baseline
Petitioners contend that FERC ignores continuing impacts and the environmental impacts caused by ongoing operation. In effect, the petitioners contend that the FPA requires the Commission to evaluate the EWEB proposal against a baseline embodying a theoretical reconstruction of what the McKenzie River basin would be like today had the Leaburg and Walterville projects not been in place for the greater part of this century. To evaluate this argument under Chevron, we first must determine whether Congress has spoken with sufficient clarity to foreclose the Commission's alternative interpretation. See Rainsong, 106 F.3d at 273.
The legislative history of the FPA supports, but does not directly sanction, the Commission's decision to use an existing-project baseline. The ECPA conference report comes nearest to evidencing congressional intent on this issue. The report states that "[i]n exercising its responsibilities in relicensing, the conferees expect FERC to take into account existing structures and facilities in providing for these nonpower and nondevelopmental values." H.R. Conf. Rep. No. 99-934, at 21-22 (1986), reprinted in 1986 U.S.C.C.A.N. at 2537, 2538. More emphatically, the report "noted that the Commission must take into account existing structures and facilities ... in relicensing proceedings under section 15." Id. at 2543 (emphasis added). The petitioners acknowledge this legislative imperative but assert that the Commission altogether excluded from consideration the environmental harms caused by these existing structures and facilities, thereby precluding "equal consideration" of non-power values as mandated by FPA section 4(e).
The petitioners also proffer excerpts from the ECPA house report in support of their position that the Commission must evaluate relicensing issues "in light of today's standards and concerns," and that "procedures and substance applicable to original licenses, including the treatment of non-developmental values, apply fully in relicensing." H.R.Rep. No. 99-507, at 33-34 (1986), reprinted in 1986 U.S.C.C.A.N. 2496, 2521. This Court's review, however, does not turn on single words or phrases in the legislative record, see United States ex rel. Fine v. Chevron, U.S.A., Inc., 72 F.3d 740, 744 (9th Cir.1995) (en banc), especially when they are taken out of context. When read conjunctively with the surrounding text, these quotations-and indeed the entire house report-display nothing more than Congress' intent to emphasize that the Commission's section 4(e) "equal consideration" responsibilities apply to relicensing as well as original licensing proceedings.
This prong of Chevron instructs us that where Congress implicitly leaves a gap for the agency to fill, there is a "delegation of authority to the agency to elucidate ... the statute." Chevron, 467 U.S. at 843-44, 104 S.Ct. at 2782. We will not substitute our own construction of the statute unless we determine that the Commission's interpretation is unreasonable. See Rainsong, 106 F.3d at 272-73 (citing Chevron, 467 U.S. at 844, 104 S.Ct. at 2782-83); accord Association of Pub. Agency Customers, 126 F.3d at 1169 ("When relevant statutes are silent on the salient question, we assume that Congress has implicitly left a void for an agency to fill. We must therefore defer to the agency's construction of its governing statutes, unless that construction is unreasonable."). Applying these principles here, we must determine whether the Commission's decision to employ an existing project baseline fills the interstices of the FPA in a permissible fashion. The Commission concluded in the Order on Rehearing that "it is highly doubtful that attempts to ascertain the status of various resources prior to the time a 50-year-old project was constructed would result in the development of any useful information." 81 Fed. Energy Reg. Comm'n Rep. (CCH) at 62,327 (citations omitted). We believe that this conclusion furnishes a reasonable interpretation of the FPA. It defies common sense and notions of pragmatism to require the Commission or license applicants to "gather information to recreate a 50-year-old environmental base upon which to make present day development decisions." 54 Fed.Reg. at 23776. The past fifty years of development in the McKenzie River Valley has reconfigured its environmental makeup, introducing changes that include differences in land use, water flows, water quality, river geomorphology, fish species composition, and fishery management practices. To the extent a hypothetical pre-project or no-project environment can be recreated, evaluation of such an environment against current conditions at best serves to describe the current cumulative effect on natural resources of these historical changes.
Nor are we persuaded by any of the petitioners' other challenges to the reasonableness of the Commission's baseline analysis. First, ODFW submits that the FPA implicitly requires a baseline consisting of a no-project minimum instream flow. This argument conflates the baseline issue with a proposed section 10(j) recommendation and must be rejected.
The petitioners premise their final argument upon a novel reading of our decision in Confederated Tribes and Bands of the Yakima Indian Nation v. Federal Energy Regulatory Comm'n, 746 F.2d 466 (9th Cir.1984). This Court has held that, in the context of an original FPA hydropower licensing, "once a project begins, the `pre-project environment' becomes a thing of the past. Evaluating the project's effect on pre-project resources is simply impossible." LaFlamme v. Federal Energy Regulatory Comm'n, 852 F.2d 389, 400 (9th Cir.1988). The petitioners, however,
Yakima presented the questions of whether the Commission violated the FPA or NEPA either when it bypassed the preparation of an environmental impact statement or when it deferred consideration of fishery protection until after it relicensed the hydropower project. See 746 F.2d at 470-75. In Yakima, we resolved both questions against the Commission, holding that the Commission must consider the environmental impacts of relicensing before issuing a new license. See id. at 475-77. In the Order on Rehearing, the Commission noted that it repeatedly has addressed the confluence between the Yakima opinion and the baseline issue. See 81 Fed. Energy Reg. Comm'n Rep. (CCH) at 62,326-27. Indeed, as early as 1989, in its regulations implementing the relicensing provisions of the ECPA, the Commission observed that:
54 Fed.Reg. at 23776.
We agree with the Commission's sensible application of Yakima, and the petitioners have cited no authority to suggest a contrary reading. Indeed, no such authority exists. Our conclusion is consistent with the opinion of the District of Columbia Circuit in United States Department of Interior v. Federal Energy Regulatory Commission in which the court described the limited reach of our decision in Yakima, stating:
952 F.2d 538, 546 (D.C.Cir.1992).
Accordingly, because the Commission's construction of the FPA offends neither the Chevron reasonableness standard nor the intent of Congress, we defer to the Commission's decision to use an existing project environmental baseline.
B. The NEPA Alternatives
Having upheld the reasonableness of the Commission's baseline, we set aside our Chevron lens and turn to the rule of reason to determine whether the Commission faithfully discharged its duties under NEPA when it evaluated alternatives to the EWEB proposal. The petitioners contend that the Commission erred when it endorsed its staff's identification of the "no-action" alternative in the final environmental impact statement as the continued operation of the Leaburg and Walterville developments under the terms of their original licenses. The petitioners assert that the proper "no-action" alternative under NEPA instead should have been the alternative of not issuing a license at all. Alternatively, the petitioners contend that the Commission violated NEPA because the range of alternatives examined by the Commission did not include license denial and subsequent project decommissioning and dam removal. These contentions fail. As discussed below, the Commission's identification and evaluation of alternatives satisfied NEPA's procedural requirements.
Under NEPA, an environmental impact statement must include "the alternative of no action." 40 C.F.R. § 1502.14(a) (1998); Association of Pub. Agency Customers, Inc., 126 F.3d at 1188. An environmental impact statement also must discuss "reasonable alternatives" to the proposed agency action. 42 U.S.C.
In the Order on Rehearing the Commission acknowledged that "[i]n the relicensing context, defining a logical `no action' alternative is difficult, because the Commission is legally required to take some action on the application for a new license, pursuant to Section 15 of the FPA." 81 Fed. Energy Reg. Comm'n Rep. (CCH) at 62,326 (quoting Public Serv. Co. of New Hampshire, 68 Fed. Energy Reg. Comm'n Rep. (CCH) ¶ 61,177, at 61,866-67 (Aug. 1, 1994)). We conclude that the statutory scheme sustains the Commission's no action definition and betrays the predominantly semantic nature of this dispute. As the Commission explained, by operation of FPA section 15(a), the effect of the Commission's taking "no action" on EWEB's relicensing application would have been to permit EWEB to continue operating the project indefinitely subject to the terms and conditions of its expired original license. See id. Section 15(a) authorizes the Commission to impose upon the relicensed party "such terms and conditions as may be authorized or required under the then existing laws and regulations." 16 U.S.C. § 808(a)(1). The Commission also may issue a "non-power license" if the public interest requires that "all or part of any licensed project should no longer be used ... for power purposes." 16 U.S.C. § 808(f); see 18 C.F.R. § 16.11 (1998). Here, the Commission logically questioned "whether license denial could appropriately be considered `no action' in the case of a relicensing .... [as d]enial would require action, rather than inaction, and would presumably be coupled with other proposed actions, such as federal takeover, issuance of a nonpower license, or project decommissioning." Order on Reh'g, 81 Fed. Energy Reg. Comm'n Rep. (CCH) at 62,326 (quoting Public Serv. Co. of New Hampshire, 68 Fed. Energy Reg. Comm'n Rep. (CCH) at 61,866-67); see also Edwards Mfg. Co., 81 Fed. Energy Reg. Comm'n Rep. (CCH) ¶ 61,255 (Nov. 25, 1997) (explaining that the decision to deny relicensing and to require dam removal constitutes a major federal action). In view of this regime, the Commission logically concluded that the "definition of the no action alternative as continued operation of the project under the same terms and conditions as the existing license simply reflects this statutory reality." Order on Reh'g, 81 Fed. Energy Reg. Comm'n Rep. (CCH) at 62,326 (quoting Public Serv. Co. of New Hampshire, 68 Fed. Energy Reg. Comm'n Rep. (CCH) at 61,867).
The Commission's choice of the terms of the original license as the no action alternative finds additional support from the Council on Environmental Quality's ("CEQ") response to Question No. 3 of its NEPA guidance memorandum.
Forty Most Asked Questions Concerning CEQ's National Environmental Policy Act Regulations, 46 Fed.Reg. 18026, 18027 (1981). We recognize that the relicensing process does not fit perfectly under the model of updating a land management plan as contemplated in the response to Question 3. Nevertheless, this Court has employed this regulatory language under analogous circumstances, see Association of Pub. Agency Customers, 126 F.3d at 1188 (holding that "CEQ regulations allow the status quo [of continuing power sales contracts] to properly be the no action alternative."), and we find nothing in the regulation to preclude its application in the hydropower relicensing context. In light of the scheme established by FPA section 15 and our decision in Association of Public Agency Customers, we conclude that the Commission properly identified the no action alternative.
We similarly reject the petitioners' contention that the Commission did not adequately examine the alternative of license denial. In the Order on Rehearing, the Commission explicitly stated that "license denial and dam removal will in most proceedings not be considered a reasonable alternative by anyone." 81 Fed. Energy Reg. Comm'n Rep. (CCH) at 62,327; see Final Environmental Impact Statement, §§ 2.5, 2.7, at 2-9 to 2-11. The Commission noted that "[d]ams, and the reservoirs they create, usually serve a variety of non-power public purposes, such as flood control, irrigation, and recreation. Moreover, ... removing a dam can have significant adverse environmental impacts." Id. at n. 13.
Here, the final environmental impact statement clearly considered the alternatives urged by the petitioners. Although the Commission never engaged in a lengthy evaluation of the dam removal alternative at any stage of the administrative process, its analysis comfortably meets the "discuss briefly" standard of 40 C.F.R. § 1502.14(a) and the rule of reason employed by this Court. In sum, we are satisfied that the Commission has taken a hard look at the range of licensing alternatives and complied with its procedural obligations under NEPA.
IV
We come to our final interpretive task. Once more, the petitioners challenge the Commission's construction of the FPA, raising two questions under related, but markedly different, statutory sections. These challenges again engender de novo review and require two distinct iterations of the Chevron standard. First, we consider whether the FPA authorizes the Commission to decide that a fish and wildlife agency recommendation submitted pursuant to section 10(j) does not qualify for treatment under that section.
A. Section 10(j)
As previously explained, the FPA establishes an elaborate regulatory regime which charges the Commission with responsibility to balance the interests of hydropower licensees and other participants in the licensing process. The processes
16 U.S.C. § 803(j)(1). Subsection 10(j)(2), however, specifies that the Commission should attempt to reconcile agency recommendations with the requirements of the FPA. See 16 U.S.C. § 803(j)(2). If, after giving due weight to these recommendations, the Commission does not adopt them, in whole or in part, the statute requires the Commission to publish the following findings (with a basis for each of the findings):
Id.
Here, our Chevron analysis begins and ends with the statute itself. We detect in section 10(j) the type of clear congressional mandate that suffices to curtail a Chevron query at step one. We are not the first court to do so. In National Wildlife Federation v. Federal Energy Regulatory Commission, 912 F.2d 1471 (D.C.Cir.1990), the District of Columbia Circuit affirmed a Commission order which had rejected agency recommendations submitted as section 10(j) conditions. Although these recommendations concerned a proposal not properly before the Commission, the court nonetheless concluded that:
Id. at 1480; see also California ex rel. State Water Resources Control Bd. v. Federal Energy Regulatory Comm'n, 966 F.2d 1541, 1550 (9th Cir.1992) (noting that the ECPA amendments require the Commission "to demonstrate why conditions proposed by fish and wildlife agencies should not be included in a license").
The petitioners cite Kelley v. Federal Energy Regulatory Commission, 96 F.3d 1482, 1487 (D.C.Cir.1996), for the proposition that the District of Columbia Circuit since has acknowledged that the reclassification issue remains an open question. In Kelley, the Michigan Department of Natural Resources ("Michigan") challenged the Commission's refusal to require license conditions that Michigan sought under section 10(j). The Director had reclassified Michigan's objections and considered them under the more permissive standards of FPA sections 4(e) and 10(a). The full Commission affirmed the Director on rehearing. At both administrative stages, the Commission failed to explain its actions through published findings as required by subsection 10(j)(2). On appeal, the court acknowledged:
Id. (emphasis added). Although Michigan's failure to preserve the issue precluded the Kelley court from resolving the question, this passage crystallizes the factual distinctions between Kelley and the District of Columbia Circuit's previous decision in National Wildlife Federation. In Kelley, the Commission left an opaque record. See id. Conversely, the administrative record in National Wildlife Federation plainly provided the reasons for the Commission's rejection and reclassification of the agency submissions. See 912 F.2d at 1480.
In our view, Kelley in no way abrogates the holding in National Wildlife Federation. Kelley at most indicates that the District of Columbia Circuit has not yet determined whether the Commission can avoid its obligation under subsection 10(j)(2) to publish its findings before rejecting agency recommendations. Although the procedural posture of Kelley abbreviated the court's inquiry, nothing left unanswered in Kelley dissuades us from adopting the sound reasoning in United States Department of Interior which withholds from the agencies a "veto power" over the section 10(j) process.
The petitioners next contend that endowing the Commission with authority to reject and reclassify agency conditions would contravene the language found in the mandatory clause of subsection 10(j)(1). In support of this contention, the petitioners invoke the rule articulated by the Supreme Court in Escondido Mut. Water Co. v. La Jolla, Rincon, San Pasqual, Pauma & Pala Band of Mission Indians, 466 U.S. 765, 104 S.Ct. 2105, 80 L.Ed.2d 753 (1984). At issue in Escondido was the pre-license certification scheme of FPA section 4(e) which permits the Secretary of the Interior to impose certain requirements on licenses issued within any Native American reservation. See 16 U.S.C. § 797(e).
Although Escondido proves dispositive in the section 18 context,
Perhaps anticipating this conclusion, the petitioners nevertheless urge that the legislative history of the ECPA amendments to the FPA cast doubt on the Commission's section 10(j) reclassification authority. We briefly essay the legislative history because the parties emphasize its importance and because we "look to legislative history in order to determine whether there is a clear indication of contrary intent." Coronado-Durazo v. INS, 123 F.3d 1322, 1325 (9th Cir.1997) (citation omitted). In so doing, we are mindful that this Court steadfastly abides by the principle that "legislative history—no matter how clear—can't override statutory text." Hearn v. Western Conference of Teamsters Pension Trust Fund, 68 F.3d 301, 304 (9th Cir.1995) (citations omitted).
Here, we find that the legislative history accompanying section 10(j) mirrors the plain language of subsection 10(j)(2) and reconfirms that Congress intended to vest the Commission with ultimate authority to reject agency recommendations improperly-lodged under section 10(j). The conference report accompanying the ECPA clearly instructs the Commission to give "the same careful and thoughtful consideration to fish and wildlife values that it gives to other purposes." H.R. Conf. Rep. No. 99-934, at 25, reprinted in 1986 U.S.C.C.A.N. 2537, 2541. The report also states, in pertinent part:
Id. (emphasis added). The conferees addressed the scope of the decisional authority vested in the Commission and declared that although agency recommendations "cannot be lightly dismissed," the Commission "is not required to adopt recommendations that are inconsistent with any other purpose of the Federal Power Act as expressed in section 4(e)." Id. at 23, reprinted in 1986 U.S.C.C.A.N. at 2540. Although we believe that the language of section 10(j), standing alone, clearly supports the Commission's actions, these passages
Given the persuasive reasoning of our sister circuit, our own interpretation of section 10(j), and the legislative history contained in the ECPA amendments, we put an end to our penultimate Chevron inquiry. Because we conclude that the statute is susceptible to only one interpretation, we reject the position advanced by the petitioners. In denying the petitions insofar as they challenge the Commission's understanding of its statutory mandate under section 10(j), our holding is narrow. We conclude that section 10(j) clearly vests in the Commission the discretion as to how or whether it will incorporate a section 10(j) recommendation received from a listed agency. As noted above, we express no opinion on the merits of the Commission's environmental findings. Moreover, we stress that nothing we have said should be construed as eviscerating the pro-environmental object beneath the ECPA amendments. The Commission must afford "significant deference to recommendations made by state (and federal) fish and wildlife agencies for the `protection, mitigation, and enhancement' of fish and wildlife." Kelley, 96 F.3d at 1486 (emphasis added). Nevertheless, Congress clearly has ordained that this deference must yield to the Commission's reasoned judgment in those instances where the parties cannot agree. Under Chevron, "that is the end of the matter." 467 U.S. at 842, 104 S.Ct. at 2781.
B. Section 18
We are met at the outset with two jurisdictional arguments from the Commission. First, the Commission contends that the petitioners lack standing to challenge the section 18 determinations. The Commission maintains that petitioners may not independently challenge the Commission's actions because only the federal intervenors, not petitioners, have rights under that section. Alternatively, the Commission contends that the petitioners' collective challenges to the section 18 rulings are not ripe for our review because the Commission's orders have left unresolved final action on many section 18 issues. These contentions have no merit.
The petitioners clearly have standing. We again borrow the District of Columbia Circuit's reasoning in United States Department of Interior, a case with a virtually identical procedural posture. See 952 F.2d at 544 n. 4. There, the court held that state agencies had parens patriae standing and the environmental organizations had organizational standing to challenge "FERC's balancing under sections 4(e) and 10(a)." Id. The court concluded that the Commission's standing arguments had no merit because the state agencies and environmental organizations made "identical substantive challenges." Id. The court rested its conclusion on the parens patriae standing of the state agencies and the organizational standing of the environmental organizations. See id.
Here, in both the administrative proceedings and in this litigation, the Departments of Commerce and Interior, American Rivers, and ODFW all urged that section 18 requires the Commission to adopt the federal agencies' fishway prescriptions without modification. ODFW has parens patriae standing. See Alfred L. Snapp & Son, Inc. v. Puerto Rico ex rel. Barez, 458 U.S. 592, 600-07, 102 S.Ct. 3260, 3265-69, 73 L.Ed.2d 995 (1982). American Rivers has organizational standing. See Sierra Club v. Morton, 405 U.S. 727, 739, 92 S.Ct. 1361, 1368, 31 L.Ed.2d 636 (1972). Accordingly, the petitioners have standing to challenge the Commission's section 18 rulings.
The Commission next argues that the disputed fishways prescriptions are not
In Steamboaters v. Federal Energy Regulatory Commission, this Court held that a Commission order "is certainly final insofar as it definitively resolves the issue whether [agency-prescribed] conditions are mandatory." 759 F.2d 1382, 1388 (9th Cir. 1985). Here, the Commission's disputed arrogation of section 18 authority turns on a discrete issue of law: whether the Commission properly may reject or reclassify fishway prescriptions submitted by the petitioners. "It is difficult to postulate an issue more proper for judicial decision than that of the statutory authority of an administrative agency." State Water Resources Control Bd., 966 F.2d at 1562. Accordingly, the section 18 issues are ripe. We thus turn to the merits and our last occasion for Chevron analysis.
We begin with the critical asymmetry in sections 18 and 10(j). Section 18 directs that the Commission "shall require the construction, maintenance, and operation by a licensee at its own expense of .. . such fishways as may be prescribed by the Secretary of the Interior or the Secretary of Commerce, as appropriate." 16 U.S.C. § 811. Conspicuously absent from this provision is a qualifying clause, such as the one in FPA subsection 10(j)(2), which expressly enables the Commission to reject a recommendation submitted under color of section 10(j). Ignoring this structural distinction, the Commission argues that we must not disturb its section 18 "findings" because the Commission fully explained on the record its reasons for rejecting the fishway prescriptions. This argument misses the mark. Section 18 on its face simply does not contemplate the two-pronged approach set forth in subsection 10(j)(2). Although the presence of a qualifying clause in subsection 10(j)(2) does not foreclose the Commission's professed authority to reject fishways prescribed by either the Secretary of Interior or Secretary of Commerce, the absence of a similar provision in section 18 suggests more than mere legislative oversight. Clearly, if Congress had wanted findings under section 18, it knew how to ask for them. See Williamson v. Commissioner, 974 F.2d 1525, 1532 (9th Cir.1992).
Taking a different tack, the Commission cautions that its statutory mission would be compromised if it were left without authority to determine whether a submission prescribes a fishway or instead constitutes a recommendation more appropriately evaluated under FPA sections 10(j) or 10(a). See generally California v. Federal Energy Regulatory Comm'n, 495 U.S. 490, 496, 110 S.Ct. 2024, 2028, 109 L.Ed.2d 474 (1990) (recognizing that the FPA represents a congressional intention to establish "a broad federal role in the development and licensing of hydroelectric power"). This argument strikes a familiar chord, for it has been rejected by every court that has considered the supposed tension between the Commission's role in the FPA relicensing process and various statutory delegations of authority to outside agencies.
In Escondido, the seminal case on this score, the Supreme Court acknowledged that FPA section 10(a) grants the Commission ultimate authority and responsibility to ensure that hydropower projects will be "best adapted" to serve a multitude of conflicting interests. See Escondido, 466 U.S. at 778 n. 21, 104 S.Ct. at 2113 n. 21.
Id. at 777, 104 S.Ct. at 2112-13. No lower court has declined to follow this aspect of the Supreme Court's decision in Escondido, and other circuits have extended the holding to other statutory provisions. See American Rivers, Inc. v. Federal Energy Regulatory Comm'n, 129 F.3d 99, 109-10 (2d Cir.1997) (applying Escondido's reasoning to section 401 of the Clean Water Act, 33 U.S.C. § 1341); Southern California Edison Co. v. Federal Energy Regulatory Comm'n, 116 F.3d 507, 512-13 (D.C.Cir.1997) (reaffirming the vitality of this aspect of Escondido in light of the ECPA amendments); Keating v. Federal Energy Regulatory Comm'n, 114 F.3d 1265, 1269-71 (D.C.Cir.1997) (same). Like these tribunals, we reject the Commission's vision of its absolute role in relicensing. Instead, we divine in the FPA a clear congressional delegation of the section 18 process to the Secretaries, exactly the sort of statutory directive that counsels a one-step Chevron inquiry.
The Commission counters by conceding that section 18, like section 4(e), reserves for the Secretaries a measure of authority to prescribe certain conditions into a hydropower license. Indeed, the Commission previously has concluded that it cannot reject, reclassify, or otherwise challenge a properly prescribed section 18 fishway. See Lynchburg Hydro Assocs., 39 Fed. Energy Reg. Comm'n Rep. (CCH) ¶ 61,079, at 61,218 (Apr. 29, 1987) ("Section 18 is mandatory and ... we must therefore require the licensee to construct, operate, and maintain fishways that the Secretary of the Interior or the Secretary of Commerce may prescribe. We have no discretionary authority in this regard; fishways must be required when properly prescribed by the Secretaries.") (emphasis added); accord Bangor Hydro-Electric Co. v. Federal Energy Regulatory Comm'n, 78 F.3d 659, 662 n. 2 (D.C.Cir.1996). Here, however, the Commission attempts to distinguish Escondido, insisting that its reasoning does not apply when what the Secretaries prescribe does not constitute a fishway.
The Commission's efforts to distinguish Escondido cannot withstand scrutiny. The Commission first relies on a portion of Escondido that does not bear on this case. The Escondido Court, in addition to its conclusion that the Commission cannot reject conditions imposed by the Secretary of Interior under section 4(e), also held that the FPA did not require the Commission to incorporate into its license several of the Secretary's conditions which applied to Native American reservations. None of the licensed facilities were located on these reservations. The Court concluded that these conditions would contravene section 4(e)'s mandate that Commission licenses issued to projects "within any reservation" shall include conditions for the "adequate protection and utilization of such reservation." Escondido, 466 U.S. at 780-81, 104 S.Ct. at 2114.
In rejecting the very same argument now forwarded by the Commission, the Second Circuit stated that "[t]his rather unremarkable [aspect of Escondido] does not support the Commission's contention that it may review and reject any state-imposed condition that it finds to be violative
The Commission next relies upon a strained reading of a post-ECPA congressional clarification of the Commission's authority regarding fishways contained in the Energy Policy Act of 1992 (the "Energy Act"), Pub.L. No. 102-486, 106 Stat. 2776 (1992). In the Energy Act, Congress explicitly considered and rejected amendments to section 18 that would have limited the Department of the Interior's authority to prescribe fishways. The Commission had asked Congress for a statutory grant of authority to consider and balance the Department of Interior's recommendations for fishways with other values. See National Energy Strategy: Hearings on H.R. 1301 et al. Before the Subcomm. on Energy & Power of the House Comm. on Energy & Commerce, 102d Cong., 1st Sess. Pt. 6 at 516-17 (1991). Congress rejected this approach. More significantly, Congress overturned the Commission's own rulemaking efforts to define fishway prescriptions. See Pub.L. 102-486, § 1701(b), 106 Stat. 3008 ("§ 1701(b)"). The Commission initially had adopted a restrictive definition of fishways that included only facilities "used for the upstream passage of fish" through a hydropower project. 56 Fed.Reg. 23,108, 23,146 (May 20, 1991). In response to public outcry over this definition, the Commission subsequently amended its rule on rehearing to embrace both upstream and downstream passage. See 56 Fed.Reg. 61,137, 61,140-45 (Dec. 2, 1991) (previously codified at 18 C.F.R. § 4.30(b)(9)(iii) (1992)). Congress promptly rejected and overturned the amended regulatory definition as still too narrow, providing:
§ 1701(b) (emphasis in original).
Despite this explicit rejection of the Commission's proposed fishways definitions, the Commission seizes upon a perceived ambiguity in the limiting clause at the end of § 1701(b) which sets forth the items which may constitute a fishway. The Commission argues that this final clause does not specify which agency is to determine whether a given prescription "constitutes a fishway under section 18." In light of this omission, the Commission, EWEB, and industry amici extensively cite the legislative history, attempting to educe from the record some indicia of support for their position. As we have explained, we canvas legislative records cautiously, for their use "as a tool for statutory interpretation suffers from a host of infirmities." Leisnoi, Inc. v. Stratman, 154 F.3d 1062, 1070 (9th Cir.1998). Distilling this morass of materials, we address only those portions of the legislative history that the Commission, industry amici, and EWEB have emphasized most strenuously.
138 Cong. Rec. S17566, S17623-24 (daily ed. Oct. 8, 1992) (statement of Senator Wallop). We accord this remark no interpretive weight. See Conroy v. Aniskoff, 507 U.S. 511, 519, 113 S.Ct. 1562, 1567, 123 L.Ed.2d 229 (1993) (Scalia, J., concurring) ("We are governed by laws, not by the intentions of legislators."); Chrysler Corp. v. Brown, 441 U.S. 281, 311, 99 S.Ct. 1705, 1722, 60 L.Ed.2d 208 (1979) ("The remarks of a single legislator, even the sponsor, are not controlling in analyzing legislative history."); Thompson v. Calderon, 151 F.3d 918, 928-29 (9th Cir.) (en banc) (Kleinfeld, J., concurring) ("[I]ndividual senators do not make laws; majorities of the House and Senate do.") (citation omitted), cert. denied, ___ U.S. ___, 119 S.Ct. 3, 141 L.Ed.2d 765 (1998).
Turning to other historical sources, the Commission offers this excerpt from the conference report to the Energy Act which stated that § 1701(b):
H.R. Conf. Rep. No. 102-1018, at 393, reprinted in 1992 U.S.C.C.A.N. 2472, 2484. The Commission has inferred from this passage that because Congress did not explicitly overrule the Commission's decision in Lynchburg, § 1701(b) "does not reflect a Congressional intent to invalidate pre-rule commission case law regarding Section 18." 81 Fed. Energy Reg. Comm'n Rep. (CCH) at 62,334 n. 50 (citing Niagara Mohawk Power Corp., 67 Fed. Energy Reg. Comm'n Rep. (CCH) ¶ 61,300, at 62,038 (June 3, 1994)). From this inference, the Commission has seen fit to expand upon the Lynchburg holding and, in the process, free itself from the shackles of Escondido. Our review of the FERC Reports reveals that the Commission has developed an extensive body of cases which consistently have held that the Commission may reject and reclassify "improperly prescribed" section 18 fishways. See, e.g., Wisconsin Pub. Serv. Corp., 82 Fed. Energy Reg. Comm'n Rep. (CCH) ¶ 61,271, at 62,064 (Mar. 16, 1998); Western Massachusetts Elec. Co., 79 Fed. Energy Reg. Comm'n Rep. (CCH) ¶ 61,007, at 61,050-51 (Apr. 4, 1997); Niagara Mohawk, 67 Fed. Energy Reg. Comm'n Rep. at 62,038-39; City of LeClaire, Iowa, 66 Fed. Energy Reg. Comm'n Rep. ¶ 61,270, at 61,663-64 (Mar. 1, 1994).
The Commission has gone too far. The Energy Act conference report simply cannot support the interpretive weight that the Commission places upon it. The report
Id. at 778 n. 21, 104 S.Ct. at 2113 n. 21; see also Wisconsin Pub. Serv. Corp. v. Federal Energy Regulatory Comm'n, 32 F.3d 1165, 1170-71 (7th Cir.1994) ("Congress has delegated to the Secretary of the Interior the authority to make a determination when and if a [section 18] fishway may become necessary."). The District of Columbia Circuit specifically has applied this framework in the section 18 context, holding that "[u]nder [section 18], FERC performs primarily as a neutral forum responsible for compiling the record for the benefit of the court of appeals. It may subsequently on review take a position or not as it wishes." Bangor Hydro-Electric, 78 F.3d at 663. We, too, find Escondido controlling in the section 18 context and therefore hold that the Commission may not modify, reject, or reclassify any prescriptions submitted by the Secretaries under color of section 18. Where the Commission disagrees with the scope of a fishway prescription, it may withhold a license altogether or voice its concerns in the court of appeals, but at the administrative stages, "it is not the Commission's role to judge the validity of [the Secretary's] position-substantially or procedurally." Id.
We note the Commission's argument that an unqualified reservation of prescription authority for the Secretaries invites a unilateral fishways determination by two agencies which do not concern themselves with the delicate economic versus environmental balancing required in every licensing. We acknowledge, as pointed out by the Commission, that the prescribing federal agencies have not promulgated regulations to guide license applicants and others in utilizing this section of the law. See Hydroelectric Relicensing Procedures: Oversight Hearing Before the Subcomm. on Water and Power of the Senate Comm. on Energy and Natural Resources, 105th Cong. 8 (1997) (testimony of Jerry L. Sabattis, Hydro Licensing Coordinator, Niagara Mohawk Power Corp.) ("Interior has never developed any regulations, procedures or standards for implementing Section 18 and has no internal appeal procedures for dealing with disputes which may arise."); 138 Cong. Rec. H11427-01 (daily ed. Oct. 5, 1992) (statement of Rep. Dingell) ("[I]t is somewhat disturbing that after so many years that [sic] the fishery agencies themselves have not prescribed regulations on their own initiative."). Nevertheless, Congress was acutely aware of the Secretaries' omission when it passed § 1701 and "[t]here is nothing in the statute or the review scheme to indicate that Congress wanted the Commission to second-guess the Secretary...." Escondido, 466 U.S. at 778-79, 104 S.Ct. at 2113. That we might disagree with Congressional failure to require such regulations, however, does not authorize us to rewrite section 18. "Our task is to apply the statute's text, not to improve upon it." Williamson, 974 F.2d at 1533 (citing Pavelic & LeFlore
V
In the end, analysis of the application is quite simple. We deny the petitions insofar as they challenge the Commission's FPA baseline analysis, its compliance with NEPA, and FERC's authority to reclassify, reject, or modify section 10(j) recommendations. Nevertheless, in light of the statutory scheme, its legislative history, and the precedent which binds this Court, we grant the petitions to the extent they challenge the Commission's construction of section 18. Accordingly, we vacate the Order Issuing New License and the Order on Rehearing and remand the case to the Commission.
PETITION GRANTED IN PART, DENIED IN PART, VACATED, AND REMANDED.
FootNotes
16 U.S.C. § 8251(b) (1994) (emphasis added).
16 U.S.C. § 797(e).
Licenses issued in past years, must be reexamined and justified at relicensing in light of today's standards and concerns. Recognizing that there may not be competing applications for many existing projects, the bill requires FERC to make this determination in every case, whether or not there are multiple applicants. The Committee intends all applicants to have knowledge of the standards under which their applications will be evaluated. Thus, in making the determination, FERC must consider a number of factors or criteria listed in the bill and, for each application, make the required findings as to each. These factors or criteria are included to guide the Commission's determination of which final proposal is best adapted. These factors or criteria are not intended to obviate the application of section 10(a) through (j) once a determination is made. Further, the criteria included in the legislation are intended to be applied in a fair and even manner and they are not to be considered by the Commission in a manner which would unfairly skew the selection process in favor of one particular applicant over another.
The Committee stresses that relicensing is not to be a "rubber stamp," non-public process. The procedures and substance applicable to original licenses, including the treatment of non-developmental values, apply fully in relicensing.
H.R.Rep. No. 99-507, at 33-34, 1986 U.S.C.C.A.N. at 2520-21.
Comment
User Comments