Judgment unanimously modified on the law and as modified affirmed without costs in accordance with the following Memorandum: Supreme Court erred in allowing Burgio & Campofelice, Inc. (defendant), the general contractor, to charge plaintiff subcontractor for the amounts defendant expended to correct a defect in the concrete floor of the auditorium that was poured by plaintiff. The subcontract provides that the general contractor must provide notice to the subcontractor...