Opinion
CORRIGAN, J.
We granted leave in these cases to determine whether defendant Michigan Public Service Commission (PSC) exceeded its statutory authority in ordering the Detroit Edison Company and Consumers Power Company to engage in "retail wheeling." We hold that the PSC lacks the authority to order retail wheeling. Therefore, we reverse the Court of Appeals and vacate the PSC order implementing the experimental retail wheeling program.
I. Factual Background and Procedural Posture
In 1992, the Association of Businesses Advocating Tariff Equity (ABATE) petitioned the PSC for an experimental retail wheeling program involving industrial customers. Under retail wheeling, the customer, or "end-user," contracts for electricity with a supplier other than the utility that owns the power lines in the geographic area in which the customer is located. The other supplier, or "third-party provider," uses the local utility's system to transmit the electricity to the end-user. The local utility is compensated for the use of its system.
Retail wheeling effectively "unbundles" a local utility's production and distribution services. Traditionally, a local utility provided a "bundled" product; it generated the electricity and transmitted it to end-users connected to its system of power lines. The industry has, however, undergone changes in recent years. Local utilities have interconnected with one another to form a nationwide grid. Thus, a utility can transmit electricity to an end-user who is not directly connected to its system. When a third-party provider supplies electricity to these end-users, the intermediate utilities are said to "wheel" electricity across their systems. A retail wheeling program requires local utilities to provide these transmission services.
Acting on ABATE's petition, a referee presided over a contested case hearing and issued a proposal for decision. The referee concluded that the PSC was not preempted by federal law from authorizing retail wheeling and that retail wheeling did not unconstitutionally impair contractual obligations. The referee further determined that, while a third-party provider need not obtain a municipal franchise under Const. 1963, art. 7, § 29, it must acquire a certificate of public convenience and necessity from the PSC under M.C.L. § 460.501 et seq.; MSA 22.141 et seq.
The referee recommended that the PSC allow retail wheeling only if the end-user's local utility agreed to provide the service. After examining the statutory framework, the referee concluded that the PSC cannot compel a utility to provide retail wheeling services, but may establish tariffs setting the price, terms, and conditions of a voluntarily provided service. The referee proposed that the PSC negotiate and authorize voluntary retail wheeling programs for Consumers Power and Detroit Edison.
The PSC rejected the referee's proposed decision, concluding that it may implement a retail wheeling program under the electric transmission act, 1909 P.A. 106 (Act
The PSC established the rates and charges for retail delivery services in its decision after remand. After the PSC modified its order on rehearing, Detroit Edison, Consumers Power, and ABATE appealed. The Attorney General cross appealed.
The Court of Appeals affirmed the PSC order in all respects.
The Court further determined that the PSC order does not infringe the utilities' right to control their management activities. The Court reasoned that utilities are not required to construct new facilities, compelled to engage in a specific management practice, or required to enter into any particular contract. Thus, the Court concluded, the PSC order is lawful and reasonable because it does not dictate the substance of management decisions. The Court of Appeals rejected the parties' other challenges to the PSC order.
This Court granted plaintiffs Consumers Power Company, Detroit Edison Company, and the Attorney General their respective
II. Discussion
The Public Service Commission has no common-law powers. It possesses only that authority granted by the Legislature. Union Carbide, supra at 146, 428 N.W.2d 322. Moreover, this Court strictly construes the statutes which confer power on the PSC. As this Court explained in Union Carbide, supra at 151, 428 N.W.2d 322, quoting Mason Co. Civic Research Council v. Mason Co., 343 Mich. 313, 326-327, 72 N.W.2d 292 (1955):
In construing the statutes empowering the PSC, this Court does not weigh the economic and public policy factors that underlie the action taken by the PSC. Retail wheeling implicates many policy concerns, from the most basic questions whether a consumer should be able to choose an electricity supplier and what market structure will ensure adequate power supply to consideration of arguable secondary effects on the environment and shareholders. See, generally, Vander Veen, Michigan is now entering a new electrical energy field: Competition, 78 Mich. B J 164 (1999). The Legislature, not this Court, is the body that must consider these questions and weigh the economic and social costs and benefits of restructuring. As this Court observed in Huron Portland Cement Co. v. Public Service Comm., 351 Mich. 255, 262, 88 N.W.2d 492 (1958):
In this case, the PSC relies on the electric transmission act,
A. Ratemaking Power
The PSC initially characterizes its retail wheeling program as ratemaking, thus falling within its authority under § 7 of the electric transmission act, M.C.L. § 460.557; MSA 22.157, and § 22 of the railroad commission act, M.C.L. § 462.22; MSA 22.41. See also M.C.L. § 460.6a; MSA 22.13(6a). The challenged portion of the order does not, however, involve ratemaking. Although retail wheeling has a ratemaking component, i.e., the establishment of the rate a third-party provider must pay to transmit power through a local utility's system, appellants do not challenge that aspect of the experimental program. Instead, appellants contend that the PSC cannot order local utilities to transmit electricity from a third-party provider's system through its own system to an end-user. This aspect of retail wheeling is simply not ratemaking.
This Court explained in Union Carbide, supra at 148, 428 N.W.2d 322, that the PSC's authority to regulate a utility's rates and charges does not include the power to make management decisions. We quoted Missouri ex rel. Southwestern Bell Telephone Co. v. Public Service Comm., 262 U.S. 276, 289, 43 S.Ct. 544, 67 L.Ed. 981 (1923), to emphasize our point:
In Union Carbide, we concluded that, although the PSC could preclude a utility from passing along increased charges incurred from its noneconomic operation of facilities, it could not order the utility to cease those operations. In other words, the PSC can encourage a specific management decision through the exercise of its ratemaking power, but it may not directly order the utility to make the decision. Similarly, in Huron Portland Cement, supra, this Court considered whether the PSC had the authority to order a utility to render service to an end-user in an area it did not serve and in which it had no power lines. This Court concluded that, absent specific statutory authority, the decision whether to provide the service rests with the utility's management. Id. at 268, 88 N.W.2d 492.
In this case, the PSC attempts to compel utilities to provide a new service — the transmission of electricity from a third-party provider's system to an end-user who is not directly connected to that system. Retail wheeling would require that utilities accept power from suppliers chosen not by management, but by an end-user, and necessitate the negotiation of new interconnection agreements or modification of existing ones. Further, the utility would have to adjust its own production and purchases of power to ensure sufficient capacity to transmit the third-party provider's electricity. Absent a statute clearly conferring on the PSC the power to order such service, the decision to provide the service lies within the province of the utility's management, not the PSC. Union Carbide, supra at 151, 428 N.W.2d 322; Huron Portland Cement, supra at 261, 88 N.W.2d 492.
B. The Public Service Commission Act
The PSC next asserts that § 6 of the public service commission act, M.C.L. § 460.6; MSA 22.13(6), grants it broad
This Court has consistently held, however, that the broad language of § 6 serves as an outline of the PSC's jurisdiction, not a grant of specific powers.
We adhered to this construction of § 6 in Union Carbide, supra at 147, 428 N.W.2d 322. Since the PSC has only those powers granted by statute and § 6 furnishes no grant of specific powers, § 6 provides no support for the PSC's order in this case.
C. The Electric Transmission Act
The PSC argues that the electric transmission act, M.C.L. § 460.551et seq.; MSA 22.151 et seq., grants it broad authority to regulate all aspects of retail electric service, including services for supplying and delivering electricity, of which retail wheeling is allegedly one. The electric transmission act was the Legislature's first foray into the field of electricity generation and transmission. Sections 1 and 2 of the act provide:
When electricity is generated or developed by steam, water or other power, within 1 county of this state, and transmitted and delivered to the consumer in the same or some other county, then the transmission and distribution of the same in or on the public highways, streets and places, the rate of charge to be made to the consumer for the electricity so transmitted and distributed and the rules and conditions of service under which said electricity shall be transmitted and distributed shall be subject
Contrary to the PSC's assertion, §§ 1 and 2 do not grant it authority to compel a utility to transmit a third-party provider's electricity through its system to an end-user. The grant of control and supervision contained in § 2 is qualified by the language "as mentioned in the first section of this act." Thus, the authority granted by § 2 does not extend beyond the subject matter enumerated in § 1.
The power to regulate the "transmission and distribution" of electricity under § 1 is limited to that "in or on the public highways, streets and places." It does not encompass a utility's lines that extend over private lands. Moreover, a requirement that a utility transmit a third-party provider's electricity does not constitute a "condition of service" under which the utility transmits and distributes electricity. In discussing the distinction between rates and services in General Telephone Co. of Michigan v. Public Service Comm., 341 Mich. 620, 636, 67 N.W.2d 882 (1954), this Court approved the following language from Elyria Telephone Co. v. Public Utilities Comm. of Ohio, 158 Ohio St. 441, 446, 110 N.E.2d 59 (1953):
As used in § 1, the term "service" plainly refers to the utility's supplying its electricity to the end-user, not the use of its lines to transmit another provider's electricity.
The word "service" has different meanings. We construe words and phrases in statutes according to the common usage of the language, but give technical words and phrases their "peculiar and appropriate" meaning. MCL 8.3a; MSA 2.212(1). Black's Law Dictionary (6th ed.) defines the term "service" in the context of public utilities as "[t]he furnishing of water, heat, light and power, etc., services by utility." That definition comports with those provided in lay dictionaries.
Thus, under any definition, the term "service" does not refer to a utility's transmission of electricity for another provider. To construe the phrase "conditions of service" as encompassing a requirement that one utility transmit another provider's electricity would require an interpretation that stretches well beyond the plain statutory language. As we reiterated in Union Carbide, supra at 151, 428 N.W.2d 322, however, the PSC has only those powers conferred by clear statutory language. The power conferred by § 1 simply does not encompass the PSC's order.
We further note that only electricity generated or developed "within 1 county of this state, and transmitted and delivered to the consumer in the same or some other county" falls within the scope of the electric transmission act. MCL 460.551; MSA 22.151. Retail wheeling often involves the transmission of electricity generated within another state. To the extent that the experimental program required utilities to wheel power supplied by an out-of-state provider, the program would clearly fall outside the scope of the electric transmission act, even if the act could be construed to grant the PSC the authority to order retail wheeling.
The PSC also relies on §§ 6 and 7 of the act, which provide, in pertinent part:
The commission shall have power in its discretion to order electric current for distribution to be delivered at a suitable primary voltage, to any city, village or township through which a transmission line or lines may pass; to order service to be rendered by any such electric utility in any case in which it will be reasonable for such service to be ordered.... [MCL 460.556; MSA 22.156.]
After investigation and hearing, the commission may by order fix the price of electricity to be charged by the electric utility within lawful limits.... The commission may establish by order rules and conditions of service that are just and reasonable. [MCL 460.557(2); MSA 22.157(2).]
These provisions do not grant the PSC broad authority to order retail wheeling. The first clause of § 6 grants the PSC the power to order that "electric current for distribution" be "delivered at a suitable primary voltage" to a city, village, or township through which its lines pass. Thus, under the plain language of the statute, the PSC has the authority to set the primary voltage at which a utility transmits electricity to an end-user. Section 6 also authorizes the PSC to order a utility to provide "service" to a city, village, or township through which its lines pass. Huron Portland Cement, supra at 265-266, 88 N.W.2d 492. It does not confer the power to order a utility to transmit electricity for another provider. Similarly, the authority to establish "rules and conditions of service" granted in § 7 must be read in conjunction with § 1. That authority clearly does not encompass the PSC's order. Accordingly, we conclude that the electric transmission act does not grant the PSC the authority to order retail wheeling.
D. The Railroad Commission Act
The PSC contends that it may order retail wheeling under § 22 of the railroad commission act, M.C.L. § 462.22; MSA 22.41, which empowers the PSC to, upon complaint, investigate and remedy unreasonable or inadequate practices and services. MCL 460.54; MSA 22.4 grants the PSC the "same measure of authority" with reference to utilities as the Michigan Railroad Commission once had over railroads under the railroad commission act. As we noted in Union Carbide, supra at 156, 428 N.W.2d 322, however, the railroad commission "did not enjoy sweeping powers...." We conclude that the PSC's commensurate authority does not include the power to require a utility to provide transmission services for third-party providers.
By statute, the Legislature required railroads to transfer and deliver freight, cars, or passengers carried on another line that are destined to a point on its line or a connecting line. MCL 462.7(a); MSA 22.26(a). As M.C.L. § 462.7(a); MSA 22.26(a) aptly demonstrates, the Legislature has expressly required that public service providers open their facilities to other providers when it deems appropriate. The Legislature recognized a similar need involving telephone service in 1913, and granted the Railroad Commission the authority to order local providers to interconnect their lines and perform switching service for the transmission of messages between the lines. 1913 P.A. 206, repealed by 1991 P.A. 179.
E. 1929 P.A. 69
The PSC further argues that the requirement under 1929 P.A. 69, M.C.L. § 460.501 et seq.; MSA 22.141 et seq., that a utility obtain a certificate of public convenience and necessity from the PSC before it renders service authorizes the PSC to encourage competition in the industry. Although the PSC has historically used its power to issue certificates to prevent, rather than promote, competition, the PSC may allow more than one utility to provide service in an area under the terms of the act. Huron Portland Cement, supra at 267, 88 N.W.2d 492. The PSC's ability to foster competition, however, does not include retail wheeling because it lacks authority to order an existing utility to share its capital facilities. As this Court observed in Huron Portland Cement, quoting Barnes, Economics of Public Utility Regulation, p. 229:
"The requirement of a certificate of convenience and necessity may enable the commission to prevent the needless multiplication of companies serving the same territory, and at the same time to avoid a wasteful duplication of capital facilities, thus keeping the investment at the lowest figure consonant with satisfactory service. By protecting the utility from unnecessary competition, the risks inherent in the utility investments are reduced and the cost of capital is thereby kept as low as the conditions of
1929 P.A. 69 does not grant the PSC the authority to order retail wheeling.
III. Conclusion
We express no view regarding the public policy implications of retail wheeling. The economic wisdom of the program is not our concern. See Huron Portland Cement, supra at 261, 88 N.W.2d 492. The question before us involves the PSC's statutory authority. We conclude that the PSC lacks statutory authority to order a utility to transmit a third-party provider's electricity through its system to a customer. Thus, the PSC lacked the statutory authority to implement the experimental retail wheeling program. We therefore reverse the judgment of the Court of Appeals and vacate the PSC order implementing the program.
WEAVER, C.J., and TAYLOR and YOUNG, JJ., concur with CORRIGAN, J.
BRICKLEY, J. (dissenting).
The majority misinterprets the statutory language relevant to this case and mistakenly characterizes retail wheeling as infringing the managerial prerogatives of the appellant utilities. For these reasons, I respectfully dissent.
I
At issue in this case is the Public Service Commission's interpretation of the statutes in which the Legislature delegated authority to the PSC to oversee electric utilities in Michigan. The majority "grant[s] no deference to the PSC interpretation in this case because the plain meaning of the statutes are controlling." Op. at 131-32, n. 8, citing Union Carbide Corp. v. Public Service Comm., 431 Mich. 135, 151, 428 N.W.2d 322 (1988).
While I agree with much of what the majority holds, I cannot agree that the relevant section of the electric transmission act has a "plain meaning."
A
The majority holds that the electric transmission act, M.C.L. § 460.551 et seq.; MSA 22.151 et seq., does not give the PSC the power to order retail wheeling. I would hold that the most reasonable interpretation of § 6 of this act gives the PSC this power. MCL 460.556; MSA 22.156.
Section 6 provides, in relevant part, that
[t]he commission shall have power in its discretion to order electric current for distribution to be delivered at a suitable primary voltage, to any city, village or township through which a transmission line or lines may pass; to order service, to be rendered by any such electric utility in any case in which it will be reasonable for such service to be ordered....
The language of this section bears repeating: the PSC has "power in its discretion to order electric current for distribution to be delivered ...." Id. (emphasis supplied).
The majority also errs in its interpretation of the second clause of § 6. In that clause, the Legislature authorized the PSC to "order service to be rendered by any such electric utility in any case in which it will be reasonable for such service to be ordered...." MCL 460.556; MSA 22.156. The majority reasons that the first two clauses of § 6 do "not confer the power to order a utility to transmit electricity for another provider." Op. at 135. The statute does not support the majority's conclusion.
"Service," as the majority notes elsewhere in its opinion, means "`[t]he furnishing of water, heat, light and power, etc., services by utility.'" Op. at 134, quoting Black's Law Dictionary (6th ed.), p. 1368. The majority looks no further into this definition, however, and concludes that the word "service" necessarily denotes the joint production and transmission of electric current. The definition of "service" is not so constrained, however, as a closer look at the majority's definition reveals.
While "service" means the "furnishing of... power," "furnish" is defined in the same dictionary as "[t]o supply, provide, or equip, for accomplishment of a particular purpose." Id. at 675.
Unlike the majority, I cannot conclude that the word "service" can only mean the joint act of producing the commodity in question and delivering it to the consumer. Indeed, the common definitions of the relevant terms allow for "service" to include separate production, separate distribution, or both together.
The majority's statutory analysis ignores the first clause of § 6, and does not take into account the full meaning of the word "service" in the second clause. Because the text of these two clauses fully supports the PSC's order in this case, I would uphold the judgment of the Court of Appeals and the order of the PSC.
B
This case also presents an important question of this state's jurisprudence: whether the agency or the courts should have the authority to determine which of several permissible interpretations should be given to an agency's jurisdictional statute. Clearly, where the language of the statute in question is plain, statutory construction is not permissible by any authority, and no real question is presented. Ludington Service Corp. v. Acting Comm'r of Ins., 444 Mich. 481, 505, 511 N.W.2d 661 (1994), amended 444 Mich. 1240, 518 N.W.2d 478 (1994); see Chevron USA, Inc. v. Natural Resources Defense Council, Inc., 467 U.S. 837, 843, n. 9, 104 S.Ct. 2778, 81 L.Ed.2d 694 (1984). As discussed in part I(A), however, that is not the situation presented by the instant case.
The majority's interpretation of § 6 of the electric transmission act is not persuasive, but I do not believe that it is impermissible under the language of the statute. The intent of the Legislature with respect to the instant controversy is not clear from the text of the statutes in question. In light of this lack of clear legislative intent, this case presents us with a good opportunity to examine how a court should determine which of two or more permissible interpretations of a statute is the proper one.
1
This Court has not always been consistent regarding the degree of deference courts should give to an agency's interpretation of the statutes the Legislature delegated that agency to enforce. The majority today recites that "this Court ordinarily accords an agency's longstanding interpretation of a statute due deference...." Op. at 131, n. 8, citing Ludington, supra at 505, 511 N.W.2d 661. This rule, in focusing on the "longstanding" nature of the interpretation in question, serves the important purpose of furthering settled expectations. Magreta v. Ambassador Steel Co., 380 Mich. 513, 521-523, 158 N.W.2d 473 (1968)(Black, J., concurring); see Wehmeier v. W E Wood Co., 377 Mich. 176, 191-192, 139 N.W.2d 733 (1966).
This Court has also noted that
"`[t]he construction given to a statute by those charged with the duty of executing it is always entitled to the most respectful consideration and ought not to be overruled without cogent reasons.'" [Magreta, supra at 519, 158 N.W.2d 473, quoting Boyer-Campbell Co. v. Fry, 271 Mich. 282,
This rule has been followed in a number of our cases, without reference to the length of time the administrative interpretation has been in existence. Adrian School Dist. v. MPSERS, 458 Mich. 326, 336, 582 N.W.2d 767 (1998); Empire Iron Mining Partnership v. Orhanen, 455 Mich. 410, 416, 565 N.W.2d 844 (1997); Breuhan v. Plymouth-Canton Comm. Schools, 425 Mich. 278, 282-283, 389 N.W.2d 85 (1986); see People ex rel Simmons v. Anderson, 198 Mich. 38, 47, 164 N.W. 481 (1917).
Some of our cases have stated that our Court, "in common with all modern courts, give[s administrative interpretations] `respectful consideration' as one of the factors to be considered in arriving at the probable legislative intent." Lorraine Cab v. Detroit, 357 Mich. 379, 384, 98 N.W.2d 607 (1959), citing Howard Pore, Inc. v. State Comm'r of Revenue, 322 Mich. 49, 33 N.W.2d 657 (1948).
In perhaps our most candid statement, we noted that appellate courts "will give the agency's construction such weight as [they] conclude[ ] is appropriate on full consideration of the statutory criteria and the record of the case on review." West Bloomfield Hosp. v. Certificate of Need Bd., 452 Mich. 515, 524, 550 N.W.2d 223 (1996). I am concerned that our standard of review of the legal interpretations of agencies is inconsistent. I believe that predictability in this area may only be achieved by determining the principles underlying such review.
2
The majority provides the firmest ground for such an underlying principle when it states that, "[i]n construing the statutes empowering the PSC, this Court does not weigh the economic and public policy factors that underlie the action taken by the PSC." Op. at 131. I agree with this statement, and I suggest that we can avoid making a policy decision in this case by recognizing the Legislature's delegation of certain policy-making authority to the PSC, and deferring to that authority.
The Legislature's ability to delegate authority to an agency is bounded only by the constitution, and there is no allegation of unconstitutional delegation of legislative authority in this case. Cf. City of Livonia v. Dep't of Social Services, 423 Mich. 466, 501-505, 378 N.W.2d 402 (1985). Therefore, given that the relevant statutory language is ambiguous, that there is no clear indication of the Legislature's intent, and that the PSC exercises some of the Legislature's policy-making authority in this area, this Court should avoid striking down the policy decision inherent in the PSC's permissible interpretation of the electric transmission act.
The United States Supreme Court has held that "the principle of deference to administrative interpretations"
The Court further stated that if the agency's choice represents
The United States Supreme Court has also extended this rule to sanction deference to an agency's interpretation of its jurisdiction under its enabling legislation, noting that "there is no discernible line between an agency's exceeding its authority and an agency's exceeding authorized application of its authority. To exceed authorized application is to exceed authority." Mississippi Power & Light Co. v. Moore, 487 U.S. 354, 381, 108 S.Ct. 2428, 101 L.Ed.2d 322 (1988) (Scalia, J., concurring and citing cases).
For these reasons, and because of a lack of reliable guideposts in determining legislative intent in this case, I would adopt a rule that this Court defer to an agency's permissible, policy-based interpretation of the statutes that it administers.
II
The majority also holds that the PSC order at issue is invalid as an infringement on the management prerogatives of the appellant utilities. Op. at 130. Because the majority's own analysis concedes that the PSC may infringe the appellant utilities' management powers if such infringement is contemplated in the PSC's enabling legislation, I disagree that the PSC's orders at issue run afoul of this Court's decisions in Huron Portland Cement Co. v. Public Service Comm., 351 Mich. 255, 88 N.W.2d 492 (1958), and Union Carbide, supra.
The majority notes that, in Union Carbide, "we concluded that, although the PSC could preclude a utility from passing along increased charges incurred from its noneconomic operation of facilities, it could not order the utility to cease those operations." Op. at 132; see Union Carbide, supra at 149-150, 428 N.W.2d 322. Our Union Carbide decision hinged on the fact that there were no specific statutes that gave the PSC the power to forbid the noneconomic operation of facilities. Union Carbide, supra at 150-162, 428 N.W.2d 322.
Furthermore, we specifically noted that the PSC's ratemaking power was sufficient to "exclude[ ] from Consumers' base rates the increased fuel costs stemming from noneconomic operation.... Thus, the commission prevented Consumers' noneconomic operation ... from adversely affecting both the utility's base rates as well as the charges passed through to ratepayers...." Id. at 149, 428 N.W.2d 322. For this reason, the PSC's ratemaking power achieved its stated purpose without shutting down the noneconomic operations, rendering any further use of that power unlawful as beyond its own terms.
Similarly, in Huron Portland Cement, we noted that "[t]his is not a case where a utility, already servicing a city, arbitrarily refuses to take on a new (or expanded) burden, for Consumers has never supplied electricity to either the city of Alpena or the Alpena area generally." Id. at 260, 88 N.W.2d 492.
We held against the PSC's exercise of power in that case because Consumers' power lines did not pass through the communities in question. Therefore, "those cases involving an undertaking of service to an area, particularly where a statute empowers the commission to order reasonable extensions of the mains and service..., are not controlling on the issue before us." Id. at 261, 88 N.W.2d 492 (citations omitted).
For these reasons, I find no guidance in either Huron Portland Cement or Union Carbide. The question in this case is determined by § 6 of the electric transmission act.
III
Because § 6 of the electric transmission act gives the PSC the authority to order retail wheeling, I respectfully dissent and would affirm the judgment of the Court of Appeals.
MICHAEL F. CAVANAGH and MARILYN J. KELLY, JJ., concur with BRICKLEY, J.
FootNotes
The statute limits the scope of the PSC's power under this section to "any city, village or township through which a transmission line or lines may pass...." MCL 460.556; MSA 22.156. Thus our decision in Huron Portland Cement Co., n. 1 supra, is consistent with this statute. In that case, we overturned a PSC order that would have compelled Consumers Power to build new transmission lines. We noted that § 6 did not give the PSC this power because "Consumers' lines do not pass through the city ... in which Huron seeks the service to be rendered." Id. at 266, 88 N.W.2d 492.
In stark contrast, the order at issue in the instant case would compel the appellant utilities to deliver electric current over their already existing transmission lines.
The Random House dictionary goes on to define "supply" as "1. to furnish or provide (a person, establishment, etc.) with what is lacking or requisite: supplying the poor with clothing. 2. to furnish or provide (something wanting or requisite): supplied needed water to the region." Random House Webster's, supra, pp. 1295, 1343. The American Heritage dictionary defines "provide" as "1. To furnish; supply: provide food and shelter for a family. 2. To make available; afford: a room that provides ample sunlight through French windows." American Heritage Dictionary, supra, p. 1458. None of these definitions carry the implication that the supplier or provider of the commodities in question had to have produced or manufactured them before providing or supplying them to the recipients.
Comment
User Comments