GTE SOUTHWEST INC. v. PUBLIC UTILITY COM'N

No. 03-97-00619-CV.

978 S.W.2d 161 (1998)

GTE SOUTHWEST INCORPORATED, Appellant, v. PUBLIC UTILITY COMMISSION and MCI Telecommunications Corporation, Appellees.

Court of Appeals of Texas, Austin.

June 18, 1998.


Attorney(s) appearing for the Case

Celina Romero, Clark, Thomas & Winters, Austin, for Appellant.

James W. Checkley, Jr., Locke Purnell Rain Harrell, Austin, for MCI.

Dan Morales, Attorney General, Andrew S. Miller, Assistant Attorney General, Austin, for PUC.

Before POWERS, KIDD and B.A. SMITH, JJ.


KIDD, Justice.

Appellant GTE Southwest ("GTE") petitioned appellee Public Utility Commission (the "Commission")1 to increase its 1996 franchise tax "pass-through" to customer-ratepayers pursuant to section 3.211(i) of the Public Regulatory Act of 1995 ("PURA 95").2 See PURA 95 § 3.211(i) (West 1997). The Commission denied GTE's request based on GTE's election to be governed by the rate-freeze provisions...

Let's get started

Leagle.com

Welcome to the leading source of independent legal reporting
Sign on now to see your case.
Or view more than 10 million decisions and orders.

  • Updated daily.
  • Uncompromising quality.
  • Complete, Accurate, Current.

Listed below are the cases that are cited in this Featured Case. Click the citation to see the full text of the cited case. Citations are also linked in the body of the Featured Case.

Cited Cases

  • No Cases Found

Listed below are those cases in which this Featured Case is cited. Click on the case name to see the full text of the citing case.

Citing Cases