TIMM, Circuit Judge.
[¶ 1] On January 3, 1995, the Public Utilities Commission (PUC) authorized Northwestern Public Service Company (NWPS) to replace Northern Electric Cooperative (NEC) as supplier of electricity to Hub City, Inc. NEC appealed to the circuit court, Fifth Judicial Circuit. There, the PUC's decision was overturned. The PUC and NWPS appeal to this Court. Here, the circuit court is affirmed.
BACKGROUND
[¶ 2] In 1977 Safeguard...