Ordered that the order is reversed, on the law, with costs, the defendant's motion for partial summary judgment is granted, and the first cause of action insofar as asserted against the defendant BAT-JAC Contracting, Inc., is dismissed.
Pursuant to Lien Law § 18, a public improvement lien is valid for a period of no more than six months from the date of the filing of the notice of lien unless an action is commenced